Update construction Poppies

Dear local residents around Poppies,

Shortly after our Christmas holidays we commenced to drill the last four drill piles for Poppies. Van ‘t Hek, the foundation construction company, then removed their equipment from the building site.

Soon Van ‘t Hek will place other equipment on the site for pressing the so-called pavers. Long steel pavers will be placed in the ground as a basis for the construction of the parking garage. We have decided to press instead of ramming these to prevent nuisance as much as possible. Pressing pavers has the advantage that much fewer vibrations are caused and the noise load will also be lower.

Pressing the pavers will take approximately 2 to 3 weeks. After this, we will excavate part of the construction pit to be able to apply the stamp windows. Then we can excavate the entire construction pit.

Thank you for your understanding on behalf of project development Edwin Oostmeijer, Mama Pioneers and Bouwbedrijf Van Bekkum.